MRP Recommendations Based on the Reorder Method

 

Expand/Collapse all Show/Hide All

MRP recommends a reorder quantity based on the reorder method selected for the make item in Inventory Management, using the following calculations:

 

Expand/Collapse item  Example - Reorder Point Reorder Method

The make item, Board-04230-33, has a quantity on hand of 10, a lead time of 7 days, and uses the Reorder Point method. The reorder point for the item is 25. The item has a sales order with 15 items required on 5/31/03 and 10 required on 6/05/03. With the MRP Accounting Date set to 5/31/03, MRP Generation will recommend making 15 items by 5/31/03, 10 by 6/5/03 and 15 by 6/7/03. The Economic Order Quantity is not considered when the item uses Reorder Point method.

 

Expand/Collapse item  Example - Economic Order Quantity Method

The make item, Board-04230-33, has a quantity on hand of 10, a lead time of 7 days, and uses the Economic Order Quantity method. The reorder point for the item is 25 and the economic order quantity is 30. The item has a sales order with 15 items required on 5/31/03 and 10 required on 6/5/03. With the MRP Accounting Date set to 5/31/03, MRP Generation will recommend making 30 by 5/31/03 and 30 by 6/05/03.

   

For more information, see The MRP Generation Process.


 