Determining Available Hours for a Work Center

 

Expand/Collapse all Show/Hide All

The available hours for a work center represent the actual physical hours in a day that a work center operates. The available hours are calculated by dividing the standard work center hours for a day by your entry in the Number of Workers/Machines field in the Work Center Maintenance window. The number of physical hours spent at a work center for an operation is determined by dividing the extended number of hours calculated for a step by the number of workers/machines. For the purpose of scheduling, it is assumed that all work centers begin a day at the same time.

Expand/Collapse item  Example 1

If 4 machines operate concurrently at a work center on an 8-hour shift, the standard hours should be set to 32 and the number of workers/machines should be set to 4. Production rate information for operation codes defined for the work center should be expressed in terms of production per machine.

As an alternative, you may want to define the production rate for operation codes in terms of production per work center instead of production per machine. In this case, the number of workers/machines should be set to 1 and the standard hours should be set to 8.

Whenever an operation is scheduled, the available hours used for scheduling must be reduced by the number of hours already scheduled for the same day. If there are no available hours left, the operation is scheduled on the following day.

 

Expand/Collapse item  Example 2

Work center A has a machine operating two shifts a day. The total number of hours available for this work center is 16. The number of workers/machines is set to 1 and the standard hours is set to 16. Work center B has a machine operating a nine-hour shift. The first step of a work order requires 10 hours of operation at work center A. The second step of the work order requires two hours of operation at work center B.

To determine the number of hours available to schedule for the second step, subtract the 10 hours spent at work center A from the 9 hours available at work center B. Because the result is a negative number, the second step is scheduled on the following day.

 

Expand/Collapse item  Example 3

If work center A has two machines operating an eight-hour shift, the capacity for the work center is still 16 hours, but the number of hours available is only 8. The number of workers/machines is set to 2, and the standard hours is set to 16.

Using the same work order as the previous example, the number of hours spent at work center A is calculated as 10 hours divided by 2, or 5 hours. The number of remaining hours for the second step is 9 minus 5, or 4 hours. Because there is time remaining, the second step can be scheduled on the same day as the first step.

 

For more information, see:

Scheduling


 

© Sage Group plc 2019. Privacy Policy | Copyright/Trademarks