Navigation

Select Work Order Main menu > Work Order Entry. In the Work Order Entry window, in the Work Order Number field, enter a work order number. Enter information for the work order. Click the Scheduling tab, and then click Schedule.

Overview

Use Schedule Dates to calculate either the calculated due date or the calculated release date. When scheduling is completed, the calculated work order release date or the calculated due date appear. If the entered release or due date was adjusted due to the shop calendar or the work center being closed, the adjusted work order release date and the adjusted due date appear.