Window Details |
|
How Do I... |
||
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
|
Related Topics |
|
|
|
|
Select Cost Type to Print |
|
|
Select Job Cost Reports menu > Job Cost Code Detail Report.
The Job Cost Code Detail Report provides a listing of cost, unit, and cost-per-unit information detailed by cost code and cost type for each job selected. This report is useful for comparing estimated and actual cost per unit, and it provides a detailed list of cost code information for a specific cost type. You can also use this report to obtain a list of all cost code items that have exceeded the estimated cost by a specified percentage.
Costs and units are reported for the period to date and job to date, along with the original and revised estimate amounts, the percentage of cost over the estimated cost, the actual percentage of job completion, the current variance, the projected cost to complete the job, and the projected cost at completion as a percentage of the job estimate.
Cost code detail options allow reporting of full cost detail by cost code and cost type or summarized by cost code, phase, or job. You can also select dollar and unit detail to include, from dollar costs only to dollar costs, units, cost per unit, and cost per job unit.
You can print the report for a specific group of cost types.You can also enter a selection of job numbers, estimators, managers, job types, sort field values and customer numbers to print.