Establishing Vendor Lead Times and Product Build Times

When you begin the IRP generation process, the system calculates the action date for each recommendation on the Inventory Requirements Planning Report by taking into account the vendor lead times and product build times. The primary vendor's lead time is defined in Item Vendors Maintenance.

For items that have a procurement type of "Make," establish a fictitious vendor name in Accounts Payable that can be selected at the Primary Vendor field in Item Maintenance. And then enter the build time for that item at the Lead Time field in Item Vendors Maintenance. If no lead time is entered for an item, the values entered in the Default Lead Time (Days) field and Default Build Time (Days) field in Inventory Requirements Planning are used.

When inventory level adjustments are recommended, the IRP generation process will use the lead time for the item plus the IRP accounting date to determine the new required date for the inventory level adjustment. The action date will be determined by the new required date less the lead or build time.

Build time is the number of days required to build a product from its components.

If Default Build Time is selected at the Calculate Build Time for Make Items Using field in Inventory Requirements Planning Options, the system uses the following hierarchy to determine the action date for scheduling "Make" items:

If Work Ticket Template is selected at the Calculate Build Time for Make Items Using field in Inventory Requirements Planning Options, the system uses the following hierarchy to determine the action date for scheduling "Make" items:

For more information, see the IRP Generation Process.