Unit of Measure Rounding Maintenance |
Window Details |
|
|||
|
|
|||
|
|
|
|
|
|
|
|
|
Select Production Management Setup menu > Unit of Measure Rounding Maintenance.
Use Unit of Measure Rounding Maintenance to specify whether to round quantities up to the next whole number when creating work tickets or work ticket steps and when material calculations do not result in whole numbers.
Enter a unit of measure (UOM) or click the Lookup button to view a list of UOMs for which rounding settings have already been defined.
Click the Unit of Measure List button to view a list of all UOMs.
Select this check box to round the value entered in a work ticket's Quantity Ordered and Quantity Planned fields to the next whole number.
Select this check box to round the calculated required materials up to the next whole number when entering a work ticket.
Select this check box to round the calculated required materials up to the next whole number during the rescaling process when entering a work ticket.