When a template for a work ticket is planned, it may often be possible to begin a step before the previous step has been completed. The degree to which a step may begin before the previous step has been completed is referred to as the overlap percentage. A 100 percent overlap means that a step is scheduled to start simultaneously with the previous step. A 25 percent overlap indicates that a step is scheduled to start when the previous step is 75 percent complete.
You can control the overlap percentage allowed for a step using the Overlap Percent field on the Work Ticket Entry Steps tab. You can also maintain the overlap percentage for a standard template step using Work Ticket Template Maintenance.
Note An overlap percentage entry for the first step in a template has no effect because there is no preceding step. Overlap percentages are also ignored when multiple activities are performed at the same center.
The first step of a work ticket requires 40 hours of time with a start date of 5/11/28, and the work center for the step is available for 8 hours a day. The second step requires 16 hours of time at a different work center that also operates for 8 hours a day. If the overlap percentage on the second step is 25 percent, the start date for the second step is calculated by backing out 10 hours (for example, 40 x 25%) from the completion of the first step. The following table compares the scheduling for the two steps first with 25 percent overlap and then without any overlap.
Date |
First Step |
Second Step with 25% Overlap |
Second Step with 0% Overlap |
5/11/28 |
8 hours |
|
|
5/12/28 |
8 hours |
|
|
5/13/28 |
8 hours |
|
|
5/14/28 |
8 hours |
2 hours |
|
5/15/28 |
8 hours |
8 hours |
|
5/16/28 |
|
6 hours |
8 hours |
5/17/28 |
|
|
8 hours |
Although the start date for the second step is 5/14/28, only 2 hours were scheduled for that day. With 0 percent overlap, the second step cannot start until the first step is completed.
For more information, see: